Project Management Oversight report highlights more than $7 billion in ongoing transit investments

March 8, 2023

22 RTA 0451

Twice a year the RTA publishes a Project Management Oversight (PMO) report that details major transit investments by CTA, Metra, and Pace and fulfills our oversight role in ensuring that we are efficient stewards of capital funding. There are 107 projects detailed in the December 2022 PMO report, representing more than $7.56 billion worth of construction, maintenance, and procurement to improve the Chicago region’s transit system. Read the full report.

Highlights from the latest PMO report include:

CTA: Non-Revenue 61st Street Rail Shop

Expected Completion: December 2023

Budget: $70,017,063

The purpose of this new project is to provide a place for storage, maintenance, and repair of over 125 pieces of equipment. This new facility is necessary as it is replacing a rail shop that was demolished in 2009. The new building will be approximately 70,000 sq. ft. and will address the various needs of non‐revenue rail equipment maintenance.

Metra: Harvey Transportation Center

Expected Design Completion: December 2023

Budget: $6,000,000

Metra is partnering with Pace for the reconstruction and rehabilitation of the Harvey Transportation Center on the Metra Electric Line. This project will include new station entrance, new platform headhouses and waiting areas, new elevators, and other upgrades that will create a better experience for public transit riders in the south suburbs.

Pace: New I-55 Garage – Plainfield

Completed December 2022

Budget: $55,385,593

Together, Pace and the Village of Plainfield have entered into an Intergovernmental Agreement (IGA) for the design and construction of a new Pace bus maintenance and storage facility. This new garage in Plainfield is necessary to support the growth of Pace’s I-55 Bus-on-Shoulder service. The construction of the facility has been completed in December of 2022 and Pace is currently running operations out of the new garage.

Together, the RTA and Service Boards report capital programs and expenditures which are detailed in the 2022 Project Management Oversight (PMO) report. Included in the details are the progress, schedule and budget for each active project.

Subscribe to our Newsletter

* indicates required
Type your email address here
What emails would you like to receive from the RTA
Tagged in: Capital Programming | PMO | Project Management Oversight | CTA | Metra | Pace | RTA | RTAMS

Related Articles

A Metra station under construction New project management oversight report highlights more than 100 projects representing $8.2 billion in capital investments

The RTA’s Project Management Oversight (PMO) program ensures that the Service Boards—CTA, Metra, and Pace—are spending capital funds and managing their infra...

June 27, 2024
Graphic that says "Transportation Tuesday, attend a four-part webinar series #TransportationTuesday" Transportation Tuesday recap: Improving and expanding the transit system strategically

With last year’s adoption of Transit is the Answer came 15 new evaluation metrics that comprise a strategy for evaluating and selecting capital projects. Now...

May 30, 2024
Navy Pier Bus Turnaround Electric Bus and Ferris Wheel 0321 Transit is the answer to meeting Illinois’ climate goals

As we celebrate Earth Day 2024, the RTA is announcing Transforming Transit —the agency’s commitment to lead the Chicago region’s transit system into the futu...

April 18, 2024
Red line extension Three years into the Infrastructure Investment and Jobs Act, Chicago’s transit system is winning competitive grants and advancing critical projects

The Infrastructure Investment and Jobs Act (IIJA), passed in 2021, represented a historic level of federal investment for shoring up the nation’s infrastruct...

March 12, 2024
22 RTA 0812 Why fully funding paratransit service and reduced fare programs is key to closing the transit budget gap

With transit facing a fiscal cliff in the coming years, fully funding critical programs like ADA paratransit service and free and reduced fare programs is on...

February 29, 2024
Pace capital RTA releases semi-annual project management oversight report highlighting more than 100 capital projects

Under its Project Management Oversight (PMO) program, the RTA ensures that the Service Boards—CTA, Metra, and Pace—are spending capital funds and managing th...